ISG Steel Mill Charge Car Approach Track Repair

Contractor returns jobsite to mill employees after only seven hours.
Posted on 09/02/2020

Project image

In October 2004 the ISG Steel Mill needed their basic oxygen furnace (BOF) charge car approach track repaired. The tracks allow all the feed materials for the BOF to be moved from stock to the furnace. The poor condition of the track was causing many problems for the mill.

Martin & McAuliffe Contractors evaluated the project and provided a schedule for the work. The mill would allow a maximum of 48 hours downtime for the BOF track repairs. Tom Roff, project manager for Martin & McAuliffe, evaluated the work to be done and concluded that a new base plate was needed. The base plate was to be 8 ft. by 20 ft. and 2 in. thick. After evaluating the time available for the removal of the old plate, installation of new anchor bolts and installation of the new plate, less than 12 hours would be available for grouting of the plate and for the grout to gain strength.

Tom Roff contacted Calumet Lumber for suggestions. After review of the job site conditions, Calumet Lumber suggested Rapid Set® UltraFlow® 4000/8 be used. The specifications called for grout to be placed 2 in. thick and allowed for a 10-hour cure window. As the project progressed it became apparent that additional grout would be needed, now to be placed at 4 in. instead of 2 in., and that the cure window for the grout to reach structure strength was reduced from 10-hours to only 8-hours.

Calumet Lumber delivered the UltraFlow grout and the project was completed with only 7 hours remaining for the grout to gain strength. Martin & McAuliffe had such confidence in UltraFlow that the site was turned back to the mill personnel on time, after only 7 hours. Loaded charge cars were traveling across the rails within minutes and the mill was able to continue operating as scheduled. Tom Roff said, “UltraFlow was easy to install, helped keep a critical project on time, and performed exactly as had been stated.”

Project at a glance
  • Project Type: Industrial
  • Application: Grouting
  • Location: Burns Harbor, IN
  • Size: 8 ft. x 20 ft. x 4 in. thick
  • Date: October 2004
  • Owner: Mittal Steel (formerly Bethlehem Steel, International Steel Group)
  • Contractor: Martin & McAuliffe Contractors
  • Product: Rapid Set® UltraFlow® 4000/8
HOW CAN WE HELP YOU?
We're with you from start to finish.

Products Mentioned